“Green Energy Corridor Power Company” (GECO) discussed the implementation of the energy corridor project passing through the Black Sea at the 15th Bucharest Forum.
Sea-news.az reports that according to GECO, the company’s CEO Yusif Gayibov and Board Member Florin Stanciu participated in a panel discussion titled “Shaping and Securing the Black Sea: Critical Energy Infrastructure for a Strategic Region.”
The event took place on November 19 at the Palace of the Parliament in Romania. The forum was organized by the Aspen Institute Romania and the German Marshall Fund of the United States under the high patronage of the President of Romania.
“During the panel discussion, Yusif Gayibov noted that the Caspian and Black Sea regions are rapidly transforming into development hubs for submarine power and telecommunications cables, port infrastructure, and offshore energy.
In this context, he highlighted the ‘Green Energy Corridor’ project, which envisages the construction of a high-voltage direct current (HVDC) transmission line connecting Azerbaijan and Georgia with Romania and Hungary via the Black Sea. The commissioning of the first interconnector line is scheduled for 2032.
The CEO of GECO also spoke about the key conditions for executing infrastructure projects of this scale. Among these, he included securing financing, regulating cross-border cooperation, developing supply chains, and ensuring the security and resilience of submarine infrastructure starting from the design stage,” the company’s statement reads.
The panel discussion also featured Chief of the Romanian Naval Forces Staff Vice Admiral Mihai Panait, State Secretary at the Ministry of Energy of Romania Marius Poșa, Meridiam representative David Delgado-Romero, OMV Petrom representative Alexandru Maximescu, and Florin Stanciu, representing “Transelectrica,” one of GECO’s shareholders.
It should be noted that the “Caspian Sea – Black Sea – Europe Green Energy Corridor” is a cross-border electricity transmission project involving Azerbaijan, Georgia, Romania, and Hungary. The foundation of the project was laid within the framework of the Strategic Partnership Agreement signed on December 17, 2022, in Bucharest with the participation of the European Commission.
The project envisages the creation of an energy corridor with a total capacity of 3.9 GW, consisting of three power lines with a capacity of 1.3 gigawatts (GW) each.